- Planning
-
-
-
- Check the survey list of machinery
- Get exact date of survey and get immobilization and inform office
- Check and prepare all necessary spares and tools
- Ensure enough manpower and time available in port
- Check previous record of maintenance.
- Check all lifting gear
- Check hydraulic pump, jacks, high pressure hose condition
- Read manual for special instruction and data.
- Carry out briefing for everyone involve, precaution, work to be done, and time available.
- Carry out risk assessment
-
-
- Tools
-
-
-
- For piston and cylinder head
-
-
- Hydraulic pump, hoses and hydraulic jacks
- Piston lifting tool and cylinder head lifting tool
- Piston inserting tool
- Stuffing box spacer
- Piston and cylinder head stand
- Piston ring expander
- Piston crown wear measuring template
2. Liner
- Liner lifting tool and liner support beam.
- Liner jack and jack support
- Liner calibration gauge
- Liner inspection ladder
- Stuffing box area covering plate
3) Chain blocks
- Check its safe load carrying capacity
- Check chain link condition
- Check free movement of chain in both direction
- Check safety lock for proper condition on hanging hook.
- Check condition of hook for sign of crack or damage
4) Eye bolts, shackles, wire sling and safety belt
- Check for safe load carrying capacity
- Check overall condition for any damage
- Check thread condition of eye and shackles
Safety during crane operation
-
-
- Don’t operate when ship is incline
- Don’t press button simultaneously
- Do not bypass limit switch to enlarge working switch
- Do not operate if someone under or on the way
- When 2 person directing, do not operate
-
- After arriving port
-
-
- On finished with engine, get immobilization permission
- Propeller clearance to be obtain form bridge
- Shut starting air system and hang notice not to start main engine
- Drain the air line, keep open
- Open indicating Cock
- Engage turning gear and turn me with manual cylinder lubrication
- After half an hour stop LO pump
- Give time to cool engine
- Open crankcase door, lock on open position and give ventilation
- Isolate jcw inlet and outlet valve for particular unit and drain.
- Isolate fuel inlet and return valve for particular unit.
- Exhaust valve spring air to isolate
- After ventilation of crankcase check, atmosphere check for oxygen content, explosive gas and toxic gas
- Enclose space entry permit to complete
- No naked light inside crankcase
- Proper lighting to be ensure inside crankcase
-
- Removal of connection
-
-
- with removal of following
- Remove exhaust bellow
- Jcw outlet pipe before the valve
- Exhaust valve spring air connection
- Hydraulic actuator high pressure pipe
- Fuel injector high pressure pipe and connection
- Starting air valve connections
-
- Removal of cylinder head
-
-
- Fit hydraulic jack on all cylinder head nuts and connect high pressure hose.
- Open jack vent and start to pump slowly
- Once air bubbles are removed, shut vent and stop pumping
- Ensure all jack vents are shut then pump to recommended pressure and stop pump
- Use tommy bar to loose nut
- Ensure all nuts are loose
- Release pressure, remove jacks and remove nuts
- Fit cylinder head lifting tool
- Lift slowly the cylinder head using ER crane
- Care to be taken when lifting, to make sure it does not come in contact with other cylinder head.
- Place the cylinder head on cylinder head stand
-
- Removal of piston
-
-
- After proper ventilation of crankcase, remove the lashing of all secure bolts and remove require pipe connection
- Turn the piston to BDC and remove piston nut and lock device
- Fit the stuffing box spacer on piston rod palm
- Remove stuffing box securing bolts and its locking device
- Remove cylinder head metal gasket
- Clean liner surface of deposits at combustion area so as piston does not get stuck during extraction.
- Turn the piston towards TDC, carefully keeping eye on turning gear ampere
- Clean the lifting holes on crown
- Fit piston lifting tool, ensure all bolt secured
- Ensure crane is in midpositon and ship is even keel
- Slowly lift up piston ensure stuffing box spacer does not get in contact with diaphragm.
- Continue to lift, ensure piston is not swinging causing piston palm get in contact with liner
- Once out, lower the piston on its stand and put cover on stuffing box housing.
- Remove the lifting tool
-
.Inspect and cleaning
-
-
- Cylinder head
-
-
-
-
- Before cleaning, check for carbon deposit.
- Any trace of water leakage
- After cleaning, crack test to be carried out at change of section (around injector bore, exh valve bore area, indicating cock, starting air valve, relief valve)
- Pressure test cylinder head cooling space
- Keep ready for survey
-
-
2. Piston and piston ring
-
-
-
- before cleaning check for carbon deposit amount and condition
- check ring condition for sticky, broken, cracks
- after taking out, carry out thorough cleaning
- check for free movement
- check ring clearance and groove clearance
-
-
3.Piston crown
- Check for burning at the top
- Use template to check
- Check for crack on top
- Piston skirt and side wall
- Check for any rubbing mark
4.Cooling passage
-
-
-
- Scaling due to poor water treatment
- Cracking due to high temperature
- Pressure test as per manual
- Take photo for before after for future reference
- Pressure test piston as per manual
- Keep ready
-
-
5.Piston rod and stuffing box
-
-
-
- Piston rod diameter to check at different point in manual
- Record and compare previous record
- Check for any scratch mark
- Overhaul stuffing box, clean all parts, and check clearance of rings.
- Take photograph
- Carry out crack test at change of section of piston rod
-
-
6.Cylinder liner
-
-
-
- Check for dryness and oiliness, clover leafing, hard particle park, polishing
- Check if scavenge port is choke & inspect
- Check for carbon deposit at top of combustion area
- Calibration to be check and recorded and compare with previous record
- Check the lubrication points for cylinder lub oil flow by pumping manually
- After cleaning, crack test to carry out around port edge.
-
-
Inspection of surveyor
-
-
-
- After cleaning and decarbonizing, all parts to be kept ready for survey.
- Overhaul stuffing box with rings renewal as required box back
- All joints, gasket and real rings renewed and kept ready.
- All calibration and measurement record are recorded and kept ready for surveyor
- Overhauled exhaust valve and fuel injector ready for box up after completion of survey
- After survey, all parts box up as per manual and system to be put in running order, take all precautions. Check for leakage and rectify accordingly.
-
-
-